project finish date

Question asked by dvrucina on Mar 1, 2012
Latest reply on Sep 5, 2014 by navzjoshi00
Hi,

I'm new to Clarity so my question is maybe answered (searched community and couldn't find appropriate answer)
Case is following: using only Clarity when you move/change latest task end date forward Clarity changes project end date to that date, but when you change latest task end date backward then project end date is not changed automatically. Why?
Any suggestions how to achieve that project end date is changed when latest task end date is changed no matter what direction it is?

Thx