Hi,

We have a need wherein we need to compute the Delay Rate of a Task (Task A), for example:

Task Name: Task A
Baseline Start Date of Baseline 1: Jan 1, 2012
Baseline Start Date of Baseline 2 (current): Jan 10, 2012

So to compute the Delay Rate of Task A, I need to subtract the 2 dates above. However, in our PRTASK table, the PRBASESTART which stores the baseline start date of a task, only stores the baseline start date of the current baseline. In example above, the PRBASESTART only stores Jan 10, 2012 unless I change the current to Baseline1.

Do you have any idea on how or where in Clarity tables can I get the Baseline Start Date of Baseline 1 without switching the version of the baseline?

Thanks a lot.