Limiting Results to Time Scaled Value Settings

Question asked by mlai on Mar 19, 2012
Latest reply on Apr 13, 2012 by AndySol
Does anyone know how to limit the RESULTS based on the settings of the Time Scaled Value grid, i.e.

I have a Portlet where the Time Scaled Value is set to:

Rolling Date = Start of the Current Week
Timescale = Weeks
Number of Periods = 9
Time Period Offset = -3

The results show Allocation and Actuals for a specific resource (as desired) BUT it is displaying ALL projects where the resource has allocations or actuals. What I'm looking to do is ONLY display projects where there are either allocations (>0) or actuals (>0), but ONLY WITHING THE PARAMETERS of the Time Scaled Value

Does anyone know how to do this?