Baseline a project with subprojects

Question asked by MatthewPalicki on Apr 25, 2012
Latest reply on Apr 27, 2012 by another_martink
We are setting up some projects to have subprojects, to represent efforts related to an overall program. We have effort attached to the WBS and Staff for each child, and also some on the parent. When we attempt to Baseline the parent, its getting messed up as it is taking all of the children, PLUS ITSELF, and creating an overall baseline for the entire hierarchy. So when we look at the parent, the baseline is way off. If we try to create a new baseline, it just adds the current total baseline back in again, and compounds the problem. See attached screenshot for more clarity. Are we doing something wrong with these baselines? Please help.