rayyan

Running a process to take a baseline for a project

Discussion created by rayyan on Jun 11, 2012
Latest reply on Jun 15, 2012 by Chris_Hackett
Hello,

We need to run a process to take a baseline for any project that reaches 20%, and another one to take a baseline whenever a certain task is completed
Now, I was able to do both, but the main show stopper here is you I want the process to be started whenever there is an update on the schedule or at least I can run this process On Schedule something like what we have in Jobs.

It only runs these two processes either "On Demand" on every project instance, and we have so many projects so we can't simply run it manually on all projects
And it will start automatically if a project field was updated (example, even if % Complete is 20%, the process will not run and take a baseline until I update the project description or any other field)

So as I said, is there anyway to run these processes for all projects, or at least when the schedule it self is updated not the project

I have CA Clarity 12.0

Thanks

Outcomes