AnsweredAssumed Answered

PMO Accelerator Question - Schedule Performance and Schec Perf -30day

Question asked by Jim_Fuhring on Jun 27, 2012
Latest reply on Jun 28, 2012 by Owen_R
We have version 12.0.6 with the PMO Accelerator installed. I have set up some test projects and seem to have some issues. So, I have some questions for you all to make sure I understand how the portlets work. Currently, Schedule Performance and Scheduled Performance - 30 day do not show the content I expect to see....

1) Critical Late tasks
2) Past Due
3) Scheduled late

Am I configuring tasks incorrectly for this portlet to identify them? My tasks have a due date and a must finish on selected. The tasks have been baselined.

Outcomes