Hello everyone, I am trying to work around the "Merge" Issue related to Cost Plans being submitted as subsequent Budget Plans ( See Related Post )

After some experimenting, I noticed that if I extract the Cost Plan Data and Create a Budget Plan to XoG in based on the extracted data, that the contents of the Source Cost Plan are the only rows/columns that exist in the new budget plan and are therefore acting as if "Replacing" everything in the prior approved Budget as opposed to "Merging".

Is there anything that I am missing?? Can someone confirm that the merging occurs at the time the user hits "Submit for Approval" ?

Thanks

Tim