Controlling contracted hours.

Question asked by Nei_Lojas_Renner_SA on Jul 17, 2012
Latest reply on Jul 19, 2012 by Nei_Lojas_Renner_SA
Hi Communitie,
I´d like to get some information about how do you use Clarity to control resources like this way:
- We’ve contracted 8000 development monthly hours (Java development) from a partner...
How can Clarity help us to store this time and make available on demand for projects?
e.g.
Project A reserves 500 dev hours… 7500hs remaining.
Project B reserves 1000 dev hours.. 6500hs remaining.

Should I create a resource/role with Availability daily time (8000hs divided by number of work days in a month) ?
Please, let me know how do you guys are using Clarity in this kind of cenario.

Nei Villas Boas