AnsweredAssumed Answered

Financial Status values - 12.1

Question asked by PallaviS on Aug 3, 2012
Latest reply on Aug 3, 2012 by another_martink
Hi,

We don't use financial part of the Project object and have hidden the Financial Status attribute from the layout. However, after recent upgrade to 12.1, we noticed that we are not able to deactivate a project anymore.
The Active attribute is greyed out. After adding the Financial Status attribute to the layout and changing the value from 'Hold' to 'Closed' , we could deactivate a project. 'Hold' is the default value for Financial Status attribute.

Since, we didn't change the default value it must have been 'Hold' even before the upgrade but we used to be able to deactivate projects. Does anybody know if the significance of 'Hold' changed from Financially inactive to Financially active in 12.1?

Thanks,
Pallavi