MSP - Clarity

Question asked by nosreme on Aug 10, 2012
Latest reply on Nov 28, 2012 by Nicolas.Sanzana-CAChile
I am seeking help to understand if there is a simple way to prevent MSP from graphically showing split tasks in the project Gantt chart. We are using clarity to capture actuals and the work hours on some task do come in on some task in discontinuous fashion....which suggests split work. However, we provide our schedule to external customer and we'd like a simple view where the task is not split. I've experimented with various settings in MSP to NOT split in progress tasks but it still doesn't solve my problem (it also seems to be not recommended by CA docs either).

Any experience on this topic is most welcomed. Goal is to not have our gantt charts displaying splits even if that is what the actuals indicate.

regard,
Patrick