Hello,

I am trying to forecast the work for a resource in MSP. In this regard, I put in the Work and the Overtime work for that resource in MSP. When I use the cost rate table, the "Cost" and the "Overtime Cost" columns are calculated and given in $ (in MSP).

For example,

Work = 50h
Overtime Work = 10h
Std Rate = $60
Overtime Rate = $20

So, Cost is calculated as 40*60 + 10*20 = $2600
Overtime Cost is 10* 20 = $200

Now, I am looking to send this information (the number of hours and the cost information) directly into the Cost plans of Clarity. How can I do that? The numbers in the "Units" and "Cost" rows of Clarity cost plans always take the "Allocation" amount in Clarity into affect and nothing else. I want to push these rates calculated in MSP to the Clarity cost plans. Is there a way that I can do it?

Thanks!!!