  • 1.  CA Clarity Tuesday Tip:  Earned Value Calculations

    Posted Aug 28, 2012 11:59 AM
      |   view attached
    Tuesday Tips: Earned Value Calculations

    We have gotten a few training issues regarding Earned Value Calculations being ‘off’. 90% of these issues are cleared up once the calculations behind the fields are understood. This information holds for 12.1.1. and higher. This information uses the default column/field labels for the EV fields. Unless stated otherwise, the calculation holds at all levels of the WBS.

    Some fields require a baseline, some do not. This has been noted. If you do not have a baseline, to see the Project Level EV information, you should add the Project Level fields to a sub page so that they can be displayed, as they will not display on the baseline view if a baseline is not present.

    A prettier word doc with this information has also been attached.

    BAC: Baseline at Completion

    BAC: (Sum of all the assignment level Actual Cost values for the project) + ETC (Cost) at the time the baseline is recorded. This will include future posted actual costs.
    Baseline required: Yes

    BCWS: Budgeted Cost of Work Scheduled

    BCWS: Sum of the BAC through a point in time. That point in time is the Project As Of Date, if set, else the current system date.
    Baseline required: Yes

    BCWP: Budgeted Cost of Work Performed (a.k.a EV)

    BCWP: Depends on the Earned Value Calculation Method
    Baseline Required: Yes


    Earned Value Calculation Method -



    Percent Complete:




    Task Level: BCWP = BAC * %Complete



    Project Level: BCWP = Sum of [BCWP] for all Level 1 Tasks



    0/100:



    If % Complete is 100, BCWP = BAC, else BCWP = 0



    50/50:



    If % Complete is > 0 but < 100, BCWP = BAC / 2



    If % Complete = 100, BCWP = BAC



    If % Complete = 0, then BCWP = 0



    Level of Effort (LOE)



    BCWP = BCWS



    Weighted Milestones - use BCWP Override field – not calculated by Clarity


    Milestone Percent Complete (PC) - use BCWP Override field – not calculated by Clarity


    Apportioned Effort (AE) - use BCWP Override field – not calculated by Clarity

    ACWP: Actual Cost of Work Performed

    ACWP: Sum of the actuals on the project through a point in time. That point in time is the Project As Of Date, if set, else the current system date. If you have future posted actuals, they will not be included in this calculation unless your As Of date is at or beyond the last date of posted actuals.
    Baseline Required: No


    Detail Task Level:
    ACWP = Sum of all assignment Actual Cost values for the task

    Summary Task:
    ACWP = Sum of ACWP for Child Tasks

    Project Level:
    ACWP = Sum of ACWP for all Level 1 Summary Tasks

    EAC: Estimate at Completion

    EAC: Aggregated Total for the cost of all actuals over time
    EAC = ACWP + [(BAC – BCWP) / CPI] where CPI = BCWP / ACWP
    Baseline Required: Yes


    EAC (T): Estimate at Completion (Cost of Total Effort)

    EAC (T) = ACWP + ETC (Cost)
    Baseline Required: No

    EAC (AT): Estimate at Completion (Atypical)

    EAC (AT) = ACWP + (BAC – BCWP)
    Baseline Required: Yes

    ETC (Cost): Cost of Estimate to Complete

    ETC (Cost) = remaining labor cost (ETC * billing rate) + remaining non-labor cost
    Baseline Required: No

    ETC (AT): Atypical cost of Estimate to Complete

    ETC (AT) = BAC – BCWP
    Baseline Required: Yes

    ETC (T): Typical cost of Estimate to Complete

    ETC (T) = (BAC – BCWP) / CPI where CPI = BCWP / ACWP
    Baseline Required: Yes

    CV: Cost Variance

    CV is the amount of what has been accomplished versus what has been spent
    CV = BCWP – ACWP
    Baseline Required: Yes

    SV: Schedule Variance

    SV is the amount of work performed versus what is scheduled to date
    SV = BCWP - BCWS
    Baseline Required: Yes

    CPI: Cost Performance Index

    CPI is the ratio of work performed to money spent
    CPI = BCWP / ACWP

    CPI >= 1 -> favorable – at or under budget

    CPI < 1 -> unfavorable – over budget
    Baseline Required: Yes

    SPI: Schedule Performance Index

    SPI is the ratio or work performed to work scheduled
    SPI =BCWP / BCWS

    SPI >= 1 -> favorable – ahead of schedule

    SPI < 1 -> unfavorable – behind schedule
    Baseline Required: Yes

    Attachment(s)

    docx
    Tuesday Tips_EV.docx   17 KB 1 version


  • 2.  RE: CA Clarity Tuesday Tip:  Earned Value Calculations

    Posted Aug 28, 2012 12:13 PM
    Thanks Jenn.
    I also like the Baseline required attribute.
    Are these the same for Clarity and OWB (when available)?

    Martti K.


  • 3.  RE: CA Clarity Tuesday Tip:  Earned Value Calculations

    Posted Aug 28, 2012 01:26 PM
    Martti,

    Yes. This should hold for OWB.

    Jenn


  • 4.  RE: CA Clarity Tuesday Tip:  Earned Value Calculations

     
    Posted Aug 28, 2012 02:47 PM
    Thanks for providing all this great info Jenn! :grin:


  • 5.  RE: CA Clarity Tuesday Tip:  Earned Value Calculations

    Posted May 15, 2013 10:38 PM
    Is there some view on clarity that can I see all this fields, or should I view on Project or other schedule tool?


  • 6.  RE: CA Clarity Tuesday Tip:  Earned Value Calculations

    Posted May 22, 2013 12:15 PM
    Don't want to be picky but in OWB help 1.21 it says
    BAC
    Defines the budget at completion, which is the budgeted cost of resource usage for the baseline plan.

    which I am more familiar than with Baseline at completion.


    Martti K.


  • 7.  Re: CA Clarity Tuesday Tip:  Earned Value Calculations

    Posted May 07, 2015 11:32 AM

    Thankyou very much for your help!

     

     



  • 8.  Re: CA Clarity Tuesday Tip:  Earned Value Calculations

    Posted May 07, 2015 11:47 AM

    Thank you. This is often misunderstood. Excellent work!



  • 9.  Re: CA Clarity Tuesday Tip:  Earned Value Calculations

    Posted Dec 20, 2016 04:31 AM

    Thank you Jenn. So helpful