AnsweredAssumed Answered

Task converted Milestone MSP 2007

Question asked by jpereza on Sep 8, 2012
Latest reply on Sep 17, 2012 by jpereza
Hi,

We have Clarity 12.1.1.1208 and apply three patches

- first patch applied 12.1.1.1
- second patch applied 12.1.1.3
- third patch applied 12.1.1.7

none of the patches has solved our problem.
We are using MSP 2007

Steps to recreate
1 create project
2 assign resource
3 0% allocation
4 create a task
5 assign task resource
6 launch MSP 2007
7 Task Is converted milestone

Then we try update Clarity from 12.1.1.7 to 12.1.2 and issue is not solved

This is related with:
CLRT-65359: MSP: When Resource Allocation is 0%, Tasks with actuals are being set as milestones upon loading into MSP from Clarity

Which is the patch or version that solve this issue?

Thanks for all,
Best regards

UPDATE: works great then of apply 12.1.1.8
Issue resolved please change status to resolved
Thanks for all

Outcomes