ramesh4028

Actual Cost showing correct value but not actual hours

Discussion created by ramesh4028 on Sep 27, 2012
Latest reply on Oct 1, 2012 by Chris_Hackett
From Peoplesoft we have received non labour actuals and loaded into clarity which we don't want to. To clear those actuals we follwed the followig steps.
Create WIP Adjustment--> Select the respective transactions for the resources--> select all--> Click on Reverse.
Approve WIP select the above transaction--> Approve
Ran the time sheet jobs.

Post Timesheets

Post Transactions to Financials

Post To Wip

Import Financial Actuals

We are able to see the changes(actuals reverted back as expected from actuals cost) in actual Cost attribute. But not in Actual Units(Still it is showing the old units).
Actual hours is still showing wrong value under Project-->Task-->WBS-->Non TS Cost-->Respective resource

Can you please let me know why it is not reverting back actuals hours? and How to revert it?

Outcomes