Target Resolution Date should be same or earlier than Impact Date ?

Question asked by leilak on Sep 27, 2012
Latest reply on Sep 28, 2012 by navzjoshi00
i am getting this error when i submit target resolution date later than Impact date.

This restriction prevents actual representation of the issue, impact, and resolution.
Example – An issue such as OTF delays are impacting dates on a project starting 9/19.
The resolution will not occur until 10/2, the next OTF cycle.
Forcing a PM to make the impact date the same or later than the resolution date misrepresents the project status.


Is there a way i can adjust this clarity created message if needed?