AnsweredAssumed Answered

% complete attribute CA Clarity

Question asked by jpereza on Oct 20, 2012
Latest reply on Sep 19, 2013 by Nicolas.Sanzana-CAChile
Hi guys,

CA Clarity PPM 12.1.2 / MSP 2010 32 bits

We have some projects with Calc Method sett = "Manual"

On Clarity % complete attribute is different % complete MSP
In Clarity % complete attribute is updated manually or automatic?, I understand that when method calc is duration or effort exist a job %complete that update the % complete of project

1 - Using calc method = Manual we should update % complete manually?

Thanks for all,
Regards

Juan

Outcomes