Work Breakdown Structure - Display Options - Automatically Expand

Question asked by shima.a on Oct 24, 2012
Latest reply on Oct 24, 2012 by another_martink
Objective: Improve the Project WBS GUI in Clarity
For Project Managers to easily manage and update information (e.g. task dates) in Clarity without having to export to Clarity
To be able to see expanded list of Tasks (at granular level) without having to always click on the + sign to expand the WBS.

After checking on the Work Breakdown Structure - Display Options - Automatically Expand checkbox, the WBS only expands up to Level 3.
Is there a way to set it to stay "expanded" at Task/Phase Level 5?

Level 1: Project Name
Level 2: Overall Summary - Project Type Name (Solution Delivery / Infrastructure / Enhancement / BAU Project Template)
Level 3: Overall Rollup of MILESTONES or WBS DETAILS
Level 4: Project Stages (e.g. Initiation / Planning / Execution / Testing / Implementation & Rollout / Closure)
Level 5: GRANULAR TASK LEVEL <---

Currently, the PM will have to click on the + sign to expand the WBS for every Page Refresh (Save / Actions-Edit / etc).

Can we keep the WBS expanded at granular level to save this effort?


Thanks,
Shima