riteshkumar

Autoschedule a Project in a Process

Discussion created by riteshkumar on Nov 8, 2012
Latest reply on Nov 15, 2012 by Chris_Hackett
Hi,

I have created a project in a step (using gel script) and I have to Autoschedule this project at a later point of time (after few other steps) by giving a specific Start/End Date

We do have an action 'Run Job' and can simply select 'Autoschedule Project' but how can I give the project Id when the parameters needs to be passed as shown in attached figure.. :blink:

Also, let me know If there is any other better way to run a job where I can give parameters dynamically (same as this scenario)

Thanks in advance..