Clarity

  • 1.  Allow assigned tasks only in Timesheet options

    Posted Nov 18, 2012 09:41 AM
    Hi,

    We are unable to see the "Allow assigned tasks only" in Timesheet options of clarity v13.1.

    Well, the help document says it should be but it is not present. So, is this some kinda bug or I'm I missing something?

    Thanks & Regards,
    Ritesh Kumar


  • 2.  RE: Allow assigned tasks only in Timesheet options
    Best Answer

    Posted Nov 18, 2012 05:07 PM
    Did not get to v13.1. to check is, but I have it in v12.1. SP1 and v13.0 SP1, but don't have it in v12.1 SP3.

    The way I reason it, it has be replaced with the the use of the following rights

    Global
    Project - Edit Project Plan - All
    Allows user to add unplanned tasks to any Project when completing his or her timesheet if he or she is a team member on that Project.

    Instance and OBS

    Project - Edit Project Plan
    Allows user to add unplanned tasks to a specific Project when completing his or her timesheet if he or she is a team member on that Project.


    Martti K.


  • 3.  RE: Allow assigned tasks only in Timesheet options

    Posted Nov 19, 2012 02:53 AM
    Hi Martti,

    Thanks for the reply.
    Yes, your reason is quite convincing..

    However, the document dint say so.. Might be CA has not updated the help documentation

    -Ritesh


  • 4.  RE: Allow assigned tasks only in Timesheet options

    Posted Nov 19, 2012 02:57 AM
    That has happened before.

    Now there is a place for bringing such items up
    MYCA Feedback community
    Technical Information / Documentation Feedback message board.
    https://communities.ca.com/web/ca-online-feedback-community/message-board/-/message_boards?_19_mbCategoryId=99130898&#p_19

    Martti K.


  • 5.  RE: Allow assigned tasks only in Timesheet options

    Posted Nov 19, 2012 03:29 AM
    Sure, Thanks Martti. -_-


  • 6.  RE: Allow assigned tasks only in Timesheet options

    Posted Nov 21, 2012 06:36 AM
    Hi All,

    It seems CA has changed the logic to implement this functionality.

    The option "Allow assigned tasks only" is removed from V13.1.
    Instead a new attribute named 'Prevent unassigned timesheet task' has been introduced for 'Project Object' which is false by default.

    The CA support folks have raised a documentation defect internally.

    -Ritesh


  • 7.  RE: Allow assigned tasks only in Timesheet options

    Posted Dec 03, 2012 12:47 PM
      |   view attached
    It is not in v.13.1


    Martti K.

    .


  • 8.  RE: Allow assigned tasks only in Timesheet options

    Posted Jan 04, 2013 11:27 AM
    Confirmed this change is also present in v 12.1 SP2. 12.1.3(5)

    Caused some headaches tracking it down.

    Tom