Actuals/ETC in Task page and Team page are not same

Question asked by PrabhuRVP on Apr 12, 2013
Latest reply on May 2, 2013 by PrabhuRVP
Hi All,

I am facing an issue on Actuals/ETC fields of Task and Team. A project with a task has different Actuals/ETC values in Task and Team page.

Project (Test) has only one Task(A), and task has only one Assignment (R1),
the task properties page has
- Actuals value = '1'
- ETC = '11'
- Total Efforts = '12'
- Loading pattern = 'Fixed'

In Assignment table ,
- PRACTSUM = '1'
- PRESTSUM = '11'

In Timesheet tables,
- Posted Actuals = '1'

In WIP tables,
- Quantity = '1'

In Team Page,
- Actuals = '9.50'
- ETC = '306.50'
- Total Usage = '316'

Team page displays the different actuals and ETC than in PRASSIGNMENT table ( PRACTSUM ,PRESTSUM). Also timesheet data is available for '1' actual only.

Please anyone help me to understand why Clarity populates wrong value.

*Actuals are calculated for days.