RonaldoRezende-TecBan

elapsed duration predecessor

Discussion created by RonaldoRezende-TecBan on May 9, 2013
Latest reply on May 10, 2013 by Chris_Hackett
I've used a predecessor in MSP with an elapsed duration. After posting scheduler on Clarity and returned to project, clarity cleared my elapsed duration. Is this a bug of Clarity?

Ex: task1 with this precedessor: 35ti+90dd
after posting in Clarity and getting back, clarity changed the predecessor to: 35ti+90d
Then my task start date was modified.

Outcomes