Hello,

I am aware that MSP recalculates the dates when the plan is downloaded from Clarity. But I am not sure what logic does it follow to change the dates. I am seeing an irregular pattern in my projects. I see that the dates are being recalculated only for the projects which has Actuals and NOT for the one which do not have Actuals loaded in them yet.

Also, for the projects which have Actuals in it, for some of them, the dates are re-calculated in MSP ONLY for the tasks which has Actuals in it whereas for some other projects, the dates are re-calculated in MSP ONLY for the tasks which do not have Actuals (and not for other tasks).

Could someone please explain this?

Gayathri