AnsweredAssumed Answered

Allocate from Estimates not working

Question asked by Nei_Lojas_Renner_SA on May 23, 2013
Latest reply on Jun 4, 2013 by Nei_Lojas_Renner_SA
Hello Community!

I have tasks with non-zero ETC (created in OWB), but when I run "Allocate from estimates" on Clarity the colum "Allocation" still shows ZERO and no allocation segments for resources appears..
I have made a test creating task in Clairty and works fine... So I think that tasks created in OWB does not have ID, and so "Allocate from estimates" does not works.
Any idea? Thanks for any kind of help!

Regards,

Nei Villas Boas

Outcomes