Find out lack of predecessors/successors

Question asked by venkitta.subramanian on Jul 3, 2013
Latest reply on Jul 5, 2013 by another_martink
Clarity R.12.1.1
OWB : 1.2.2

We have told the PMs that every single task should have both predecessors/successors except the very first and last task.

In a project, we have thousands of tasks/milestones in the WBS and I was wondering, is there anyway to find out how many tasks are lacking either predecessors or successors?

I have a custom OWB will show up the tasks with no dependency set up but I wanted to get only those tasks not using either one.

Any help is greatly appreciated

Thanks
-Venkitta