can we change the finish date for task which is completed ?

Question asked by supriya.chakraborty on Sep 25, 2013
Latest reply on Sep 26, 2013 by supriya.chakraborty
Hi ,

I wanted to get an confirmation whether we can change the finish date of already completed task which is not a milestone from UI ,so that the task finish date is extended and people can post their time sheet.
I tried tweaking with the Actual Finish Date by changing it ..but it didnt change the task end date .
For the completed task the finish date is uneditable.
As far as i know it is not possible .
Any comments would of great help !!
We are in 12.1.3 version

Regards,
Supriyo