Hi, need your expertise on this. I have an appl that is in applhold i will release it after sometime but i want the two jobs in it to be bypassed. How can i code it without using REXX?

JOB CHECKJOB1 TASK
RUN DAILY
REXXON
TRACE N
N=JOBONCSF('JOBZ','Z')
N=JOBONCSF('JOBX','X')
F=0
DO J = 1 TO N
IF ZPNODE.J = 'PREDWAIT' THEN F=1
END
DO J = 1 TO N
IF XPNODE.J = 'PREDWAIT' THEN F=1
END
"X="F
REXXOFF
IF %X=1 THEN DO
ESP AJ CHECKJOB1 COMPLETE APPL(%ESPAPPL..%ESPAPGEN)
ESP AJ JOBZ BYPASS APPL(APPL1)
ESP AJ JOBX BYPASS APPL(APPL1)
ENDDO
ELSE DO
IF %X=0 THEN DO
ESP AJ CHECKJOB1 COMPLETE APPL(%ESPAPPL..%ESPAPGEN)
ENDDO
ENDDO
ENDDO
ENDDO
ENDJOB