Unable to Edit the Task Finish Date

Question asked by trajesh on Dec 12, 2013
Latest reply on Dec 13, 2013 by another_martink

Hi All,

I have Task which has start date:1st DEC 2012 and Finish Date 10th Dec 2013 the task is fixed Duration and Its loading Pattern is couner.The Task Has Actuals posted on it till 10th DEC 2013.Now i want to change the TAsk finsih date.When i do it by adding some ETC to the Task it was changing  in OWB, but when i save the project back to clarity and open again i see the date was not changing.

Can any one please tell me how to chage the fixed duration Task Finish Date.

 

Thanks

Rajesh