AnsweredAssumed Answered

delay replenishment renewable resource

Question asked by vzautobot on Jan 1, 2014
Latest reply on Jan 1, 2014 by mattbart

I know that a job will automatically return a resource once it completes if the resource is renewable.   Is there any way to delay the return of that resource and instead have another job replenish it?  I do not want to change the resource type if I dont need to.   If a depleatable is required, what is the statement to use which will restock the resource?

 

Outcomes