Task start and finish date changes after posting timesheets

Question asked by Vit_Posel on Feb 3, 2014
Latest reply on Feb 3, 2014 by Vit_Posel

We have tasks with assignment for each task one resource.

example task QS2

Task 13.1. - 24.1.

Assigned ressource with ETC 20

We made timesheet for 20 - 23.1 -  6 hours for every day 24 i total

Approved timesheet and job "post timesheets" started.

------

Task start and finish dates changed:

start 20 finish 23 - like there are timesheeted.

In previous versions was changed only ressource assignment start and finish dates not task start and finish date.

Has anybody idea how to prevent this?