AnsweredAssumed Answered

MSP 2013 base line issues with Clarity 13.3

Question asked by Slovak on May 19, 2014
Latest reply on Dec 29, 2014 by navzjoshi00

All

We have installed Clarity 13.3.0.286 03 11

I have MSP 2013 installed. I can take a project from Clarity to MSP 2013 that IS NOT baselined. It pulls up fine and I can upload it  back to CLarity fine.


When I attempt to pull a project from Clarity to MSP 2013 that is BASELINED, it starts to pull dowm the tasks etc. Then the popup states" down loading baseline" it just hangs and a pop up comes up "Schedlink MFC Application has stoped working". Tells me to close program.

 

Is there a fix for MSP 2013 vs. CLarity version 13.3.0.286 03 11 regarding baselined projects??

 

MIke

 

Outcomes