Hi Everyone,

i am hoping that someone can help with this, I have a user that blew up a project plan in 7.5.3 in July and 5 months later, reporting on that project plan is now and issue because the wbs has been corrupted and I can only get the task name, resource and hours out of Clarity. Is there any way to restore the WBS on this project plan or retrieve it on the back end from the oracle tables? The only reason that it's an issue now is that a particular group at my Co. only reports quarterly and has brought it to my attention.

Thanks