AnsweredAssumed Answered

Calculation in Clarity for IRR & NPV

Question asked by Aanish on Mar 24, 2011
Latest reply on Mar 25, 2011 by navzjoshi00
We are trying to calculate NPV and IRR in Clarity. We know its an option on the "budget" page on projects in Clarity. However we cannot use the budget page because we need to include depreciation & tax details when calculating NPV and IRR & most importantly need the extra features the cost/benefit plans provide.

Is there is a way to include depreciation & tax information using transaction classes to impact the NPV & IRR calculations?

We also know that its possibly to include expense type on the transaction entry as depreciation but it does not seem to have any logic tied to it and there are tax details in the rate matrix but they dont seem to apply to apply to NPV calculations. Hoping there is more here in Clarity that can help us with these calculations.

Thanks!