AnsweredAssumed Answered

Clarity to MSP thresholds

Question asked by pete.gallagher on May 18, 2011
Latest reply on May 23, 2011 by lisa_kollin
What are your expectation for load times when opening a project from Clarity to MSP? What are your load/save thresholds for small, medium and large projects/programs? We have defined small as <25 tasks (generally KLO projects), medium >25 and <200, and large >200 or master projects and programs. If you experienced long load/save times, how did you overcome the issues.

Our platform is AIX, Websphere, MSP2007

Should it take minutes to load a project into MSP?

Outcomes