AnsweredAssumed Answered

Resource Delays on Tasks

Question asked by karen_beaudouin on May 18, 2011
Latest reply on Apr 30, 2014 by Dale_Stockman
After we upgraded our systems to Calrity v12 and MS Project 2007 on the first of January, I notice that when a resource does not charge time to an active task, no delay is being placed on the resource.

Further with resources who have charged time at the start of the task, but then do not enter time in future weeks, their ETC does not get advanced either.

The result is that the resource's hours do not move forward and the project shows that I have etc's in the past.

Can you tell me is this related to resource constraints in Clarity or MSP?

Did we miss a switch setting when we did the upgrade?

Thanks!

Outcomes