AnsweredAssumed Answered

% Completion rollup from children to a Summary (parent) WBS

Question asked by stct80 on Jun 20, 2011
Latest reply on Apr 18, 2016 by Michael Thibault
Greetings!

We observed inconsistent result with % Completion rollup from children WBS to the parent, when project is opened from Clarity into OWB. Similar disconnect is observed while opening into MS Project (Its a different project than the one which is defined for OWB interface). Most of the cases, % Completion is 0 (not rolling up appropriate number from lower level). Results are almost similar when roll up is reported thro Clarity web UI (Project > Task page).

I heard this could be due to 8.1 version and later versions have this fixed. Is this correct, or there is some some configuration setting?

Can someone pls advise on this?

Thanks in advance,