AnsweredAssumed Answered

Resource availability rate and calendars

Question asked by mmorey on May 1, 2008
Latest reply on Apr 29, 2014 by another_martink
when you create a resource you assign an availability rate which represents the number of hours of work per day.   What is the interaction or impact between this value, the calendar shift settings and availablity?   In other words if a person is working 9 hours per day, does the shift calendar have to reflect a 9 hour work shift and whcih one influences the availablity calculation?[left]

Outcomes