ETC on Assignment?

Question asked by Chris_Shaffer_hcsc on Mar 25, 2009
Latest reply on Mar 30, 2009 by Chris_Shaffer_hcsc
Hello all, I may be overlooking something small but how in the world do I xog in ETC's to a resources assignment? XOG Updates the project but when I look at the assignement, there are no ETC's. HELP...   TaskLabor actualWork="0" baselineWork  ="0" estPattern="1" start="2010-03-01T08:00:00"  finish="2010-04-23T17:00:00" remainingWork ="188.8888889" resourceID="262636" unpostedActuals="0">   TaskLabor >