How does my ETC always increased when I assign more resources?

Question asked by Ramg on Oct 9, 2009
Latest reply on Oct 10, 2009 by Paul_Maxwell
I have created a new Task in Clarity with Start and End date of 10/5/2009 - 10/9/2009(Mon-Friday). I assigned a resource(100% allocated) initially and the ETC was automatically generated to 5 days and when I added another resource(100% allocated) and the ETC increased to 10days. In general Microsoft project reduces to 2.5 as two resources are assigned to the task.        