NBI_PM_PT_FACTS table

Question asked by wboodras on Feb 24, 2010
Latest reply on Feb 25, 2010 by wboodras
I would like to see allocation data out  36 months in the future (don't ask, business demand).   To accomodate that, I have changed the time slice MONTHLYRESOURCEALLOCCURVE to have From Date 2/1/2009, Slice Period = Monthly, Number of Period = 48, Item = Allocation.   I was then expecting to see data for the date range I specified in my slice within the NBI_PM_PT_FACTS table after running the Datamart Extraction and Datamart Rollup job.   However, I am only seeing data up to current month, no future data is available in the table.   Where did I go wrong?