AnsweredAssumed Answered

Cannot update Tasks in Workbench

Question asked by armsct48 on Mar 29, 2010
Latest reply on Apr 1, 2010 by Paul_Maxwell
All,  I have a project active in Workbench.   It was baselined a couple of times.   The project manager would like to update two tasks - need tro move the date out from 3/26/10 to 4/15/10.   Workbench is not allowing the two tasks to be updated.   Any ideas why?   The two tasks are "fixed" tasks.   I have a screen shot in a word document that I've attached for reference.   Thanks for your help!

Outcomes