EV calculation

Question asked by juu on Mar 4, 2015
Latest reply on Apr 2, 2015 by samos2

I found that when assign ETC in task level with charge and
non-charge code in task level. Also, rate matrix is configured for non-charge rate.

 

ETC Total is 85.50 (including non-charge code for 10 hours)

 

  1. When create Cost Plan with Task assignment, ETC is rounded up and used
    for cost calculation.  How to fix the unit decimal in cost plan ?
  2. EAC in schedule and performance is also rounded up.
  3. When run earned value update job, Cost is not exclude for non-charge
    task. Is it correct ??  If yes, what is propose for that ?

1.jpg

2.jpg

 

3.jpg

4.jpg