AnsweredAssumed Answered

Project Rate Matrix Associations

Question asked by whole_milk on Jul 7, 2015
Latest reply on Jul 16, 2015 by whole_milk

Team:

 

Let's say we have two entities:

1. APPLE

2. ORANGE

 

Apple has its own fiscal TP's, plan defaults, apple rate matrix and department OBS

 

Orange has its own fiscal TP's, plan defaults, apple rate matrix and department OBS

 

We also have two partitions - APPLE and ORANGE

 

When I create a project in ORANGE partition, my expectation is that it should have the ORANGE rate matrix as the labor matrix by default in the financial sub-page. But the matrix showing up is APPLE. Any idea what may be going wrong??

 

Is there any place in the system where partition and entity may be linked???

Outcomes