Hello, How's everybody? I contact with the Clarity community because I need to know if is possible to change the position of any milestones because when a user create a milestone after create a task that the effort is one day, and use a dependence (end-beginning), the milestone appear under the task, and this is correct, but appear at the beginning when should appear at the end.

 

Aditional Information:

The field "% Complete Calculation" have the option "Duration" because we not use the user capacity functionality.

 

I take a capture to understand this issue.

Milestone visual issue.jpg