AnsweredAssumed Answered

Join "Stage" field with the phases of the Gantt

Question asked by Patricio_1979 on Jul 28, 2015
Latest reply on Aug 10, 2015 by Patricio_1979

Hello community , I contact with you in the case because we need to develop a process that allow update the field "Stage" when a user set a complete phase in the Clarity Gantt.

 

For example, if you complete all tasks of the phase "En Analisis".

Imagen 1.jpg

Imagen 2.jpg

 

When the "***" process detected that this fase appear "Complete", then updated the field "stage" with the value "En Analisis".

Imagen 3.jpg


For us is very important create this type of connection between both "worlds", to keep aligned the gantt programming with the field "Stage".

Someone development a similar process or can tell me if is possible create a process that link this objects (Task and Project ).

 

Regards.

Patricio.

Outcomes