Discrepancy in Planned allocation and Allocation

Question asked by Uruj on Aug 18, 2015
Latest reply on Aug 18, 2015 by Uruj

Hi,

 

Following planned allocations are made:

 

01/06/2015-31/07/2015-->0%

01/08/2015-31/08/2015-->60%

01/09/2015-31/10/2015-->100%

01/11/2015-31/10/2015-->0%

 

The resource's hire date is 10-Aug-2015, and has no holiday after that (One day=7.5 hours). Total working days for august including 10th Aug are 16 days.

 

But in allocations, it is calculation 48% only i.e. 72 hours (instead of 120 hours).

 

What could be the reason? Have checked, that no other allocations are made for this resource during this time.

 

Regards,

Uruj