Program Start date is not getting updated on changing the Start date for project (sub to a program)

Question asked by Hari_SNR on Mar 9, 2016
Latest reply on Mar 15, 2016 by Michael Thibault

eg:  A is a Program and B is a Project with A as master.

Start field (schedule_start column on  INV_INVESTMENTS table )value for A is 1/1/2013

Start field value for B is 2/2/2013

 

Functionality on 13.1:

on updating start field for B to 1/1/2012(date prior to original start date)

Start field for A also changes to 1/1/2012

 

On upgrade to version 14.3

on updating start field for B to 1/1/2012(date prior to original start date)

Start field value for A remains  1/1/2013.