AnsweredAssumed Answered

Resource Requisition

Question asked by Uruj on May 5, 2016
Latest reply on Jun 24, 2016 by Chris_Hackett

When project manger creates a requisition for resource then it goes to booking manager. then booking manger updates the allocation segments according to availability of resource and propose this requisition. the again request goes back to PM for approval. PM gets the notification with a link to accept requisition. after opening this link PM is not getting any option to accept or reject the requisition. is there any specific right that needs to be given for this?

If "resource- hardbook" right is given to PM then he is getting the option to book or reject the proposed requisition. but if this right is given then there is no mean to use requisition. PM can always edit the hard allocation even that is not approved by booking manager. so i think there should be any other right that needs to be given.

Outcomes