What is Days Late. what does it represents?

Question asked by JayaSantoshKumar on May 12, 2016
Latest reply on May 12, 2016 by urmas

Hi Everyone.

I'm working on a Milestones report using DWH tables where DWH_INV_TASK  table has Days Late Column to be displayed in it.
I have gone through its description , but i didn't understand it clearly.

 

Days Late:- WBS record days late. If the status is not Completed and the WBS record is baselined, then days late = baseline finish date - finish date. If the status is not Completed and the WBS record is not baselined, then days late = today - finish date.

 

Here is my report output and application screen shots and report was run on 12/05/16

Could you please go through the attached screen shots

 

Thanks,

Santosh.