Project Storyboard - Budgeted Cost Incorrect -Time Slices?

Question asked by James_Teh Employee on Jun 16, 2016
Latest reply on Jun 27, 2016 by Jerin_Sebastian

I have an approved, Plan of Record Budget Plan totalling $370,000.

Annual time periods, and the $370,000 is spread across 2016 and 2017:

 

However when I run the PMO Accelerator Project Storyboard report in Jasper Advanced Reporting., the Budgeted Cost is coming up as $31,394.

I think this is a time-slice issue? Annual Time slices not going out far enough?

What time slice should I edit for Jasper / the Data Warehouse to have the full amount/time scale?

 

On the entity, I have checked annual fiscal time periods are active.