Hi All,

 

Resource A is added to the Team and given 100% allocation for this November month and Allocation of 189 was populated in the Team Tab --> Detail, but ETC is showing as 39(ETC is configured in the List layout).

 

I have checked the same in Test environment , then as per his availabilty the allocation and ETC are 159.5.

 

Please Advice.